VIDEO: MBTA Presentation – Wollaston Station Renovations – April 4, 2017 – 80 Clay St – Top Floor


Wollaston Station
• Opened in 1971 – Old Colony Corridor
• 4,624 Daily Boardings
– 60% Pedestrians
– 40% Drive or Drop-off
• Parking Lot (538 Spaces)
– 100% Usage

Wollaston Station Project Purpose
• Accessibility
• Code Required Upgrades
• Site and Utility Improvements
• State of Good Repair
• Modernization

Wollaston Station Project Scope
• Accessibility
– Constructs new fully accessible path to a center island platform elevated 13 feet above street level.
• Structural Upgrades
– New Platform Slab & New Platform Canopy
• Bridge Access to platform
• New South Stair to Renovated Lobby
• Track Rehabilitation
• Station Electrical Service Upgrade
• Upgraded Utilities

20-Month Station Closure
– Fall 2017 to Summer 2019
– No station boarding or disembarking.
– 423 of 538 spaces remain available for parking.
– Red Line Service continues through station

Red Line Closures
– Weekend Diversions
– Early access, no service after 9PM, M-F.

Red Line Single Track Operations
– Single Track at N. Quincy and Wollaston after 9PM

Mitigation:
Provide a dedicated bus route:
• Wollaston to North Quincy with current headways
• Provide two accessible stops at Wollaston with temporary shelters, lighting & snow removal
North Quincy Parking
• On-site and Off-site Options
• Commander Shea Boulevard extension
• Traffic Management Police Detail at Neponset Circle
• Assistance with Ferry Service

Anticipated Construction
o April 2017 Advertise for Bids
o July 2017 Notice to Proceed
o Fall 2017 Station Closure
o Summer 2019 Reopen (Fully Occupy)
o Winter 2020 Project Complete


Link to COMPLETE MBTA Wollaston Powerpoint Presentation