Fore River Bridge Replacement Public Meeting – May 18th, 2017 at 6:30PM at the Fore River Clubhouse

Project Working Hours

Beginning on June 2nd, the project will move to working 2, 10-hour shifts, Monday to Saturday. This change will help speed up the transition from the current temporary bridge to its permanent replacement and lessen the traffic impacts associated with this work. For more information, please see below in “Construction Underway.”

Construction Underway – Transitioning to the Permanent Bridge

Beginning on June 2nd, 2017, the project team will begin transferring traffic from the existing temporary bridge to its permanent replacement. Due to the location of the temporary bridge next to the permanent structure, lanes reductions are required for this work. Drivers should anticipate the following:

  • Between June 2nd and August 31st: there will be one lane of traffic in each direction on the Fore River Bridge.
  • Between September 1st and September 30th: there will be three total lanes of traffic on the Fore River Bridge. During the morning peak commute, there will be two lanes in the northbound direction and one lane in the southbound direction in order to accommodate travelers heading into Boston. The traffic arrangement will then be shifted during the evening commute to allow for two lanes in the southbound direction and one lane heading northbound.
  • After October 1st: all four lanes of traffic will open on the new bridge. The temporary structure will go out of service completely at this time.

This fact sheet provides more information about the transition from the temporary bridge to the permanent structure.

Construction Underway – Traffic Impacts

Through its public involvement process, MassDOT has learned that the most likely alternate route for those familiar with the Quincy/Weymouth area and seeking to avoid the Fore River Bridge is via the Southern Artery, Quincy Avenue, Commercial Street, and North Street. The agency and its project team are aware that this will send traffic through the already busy Weymouth Landing. To keep traffic moving, the project team has already or will before June 2nd, 2017, undertake the following steps:

  • Made physical or signal timing changes at intersections along the most likely alternate route.
  • Coordinated with the Towns of Braintree and Weymouth and the City of Quincy to provide police details to keep traffic moving along the most likely alternate route.
  • Placed changable message boards at points along 3A to the north and south of the bridge indicating points at which drivers can divert to large, regional roads like Route 3, and travel times over the bridge.

Please Come Join Us:

You have two opportunities in public information meetings to learn more about the upcoming work at the Fore River Bridge:

  • In Quincy: on May 18th, 2017 at 6:30PM at the Fore River Clubhouse located at 16 Nevada Road
  • In Weymouth: on May 23rd, 2017 at 6:30PM at the Abigail Adams Middle School located at 89 Middle Street

As of the week of May 8th, construction for the new Fore River Bridge is ongoing. Learn more on our progress reporting page.

Replacement of the Fore River Bridge is a signature project of the Commonwealth’s historic Accelerated Bridge Program. The replacement bridge will carry Route 3A, known as Washington Street in Quincy and Bridge Street in Weymouth, over the Fore River.

The project team invites you to peruse the website, discover more about the project; browse the materials developed to support the public involvement process or contact the project’s public involvement specialist.

If you have immediate questions or concerns regarding a specific construction activity at the Fore River Bridge site please follow this link for contact information.

Accommodating All Users During Construction

MassDOT understands the importance of the Fore River Bridge to the Route 3A corridor. During much of construction, the temporary bridge can be kept open at full capacity, limiting impacts to commuters and abutters. Any reductions in capacity will take place with significant advanced notice through the methods outlined above and in coordination with the City of Quincy, Town of Weymouth, and MBTA which operates a bus route over the bridge and ferry service beneath it. Access to adjacent businesses will be maintained throughout construction. We urge you to visit the websites of the Quincy Chamber of Commerce and South Shore Chamber of Commerce to learn more about the many businesses near the bridge that will remain open throughout construction.

The agency and its design/build team are also well aware of the Fore River’s important role as a working river and will coordinate with the United States Coast Guard and the marine units of Quincy and Weymouth to ensure that waterborne traffic continues to move smoothly throughout the construction process.